Greatham 1&2 Restructure, Demoition Works
Baker Mallett has been involved in compiling the sanction estimate for Huntsman Tioxide.
The project commenced in June 2002 and was completed in December 2006. The project includes the Divinatory of the existing plants and the decontamination of existing piperack equipment.
The decontaminated piperack and equipment had to be dismantled before the demolition of the plant could commence. Restructuring of the existing Infrastructure works also formed part of the Project.
Baker Mallett provided traditional pre and post contract quantity Surveying services together with Cost Engineering and Estimating Services throughout the duration of the project.
Discipline: Cost Engineering/Estimating