Baker Mallett has been appointed by Austin Friars St Monica’s School the role of Quantity Surveyors and CDM Coordinators on the construction of a new all weather hockey pitch at Austin Friars St Monica’s School.
The project involves the construction of a full sized, sand dressed, synthetic grass hockey pitch including drainage, ball stop fencing, floodlighting and retaining wall.
The Contractor on the project is Border Construction Ltd and the scheme started on site on 14 April 2008 and was completed October 2008.
- Discipline: Quantity Surveyors, CDM Coordinator
- Project Value: £675,000
- Form of Contract: JCT Intermediate Building Contract, 2005 edition